Work Center Schedule
Form ID: (AM000001)
This form displays the production schedule for each work center by date and time. The schedule includes planned orders generated by MRP. Both MRP planned and actual production orders are initially scheduled using infinite capacity when created. You can use the Rough Cut Planning (AM501000) form to finitely schedule production orders.
This form is available only when the Advanced Planning and Scheduling feature is enabled on the Enable/Disable Features (CS100000) form.
Form Toolbar
The form toolbar includes only standard buttons. For the list of standard buttons, see Form Toolbar and More Menu.
Selection Area
By using the elements in this area, you can specify the selection criteria to show the scheduled orders in the table.
Element | Description |
---|---|
Warehouse | Select the warehouse or leave this box blank to view the schedule orders for all warehouses. This box appears only if the Multiple Warehouse feature is enabled on the Enable/Disable Features (CS100000) form. |
Work Center | Select the work center or leave this box blank to view the scheduled orders for all work centers. |
Order Type | Select the order type or leave this box blank to view the schedule for all order types. |
Production Nbr. | Select the production order number or leave this box blank to view the schedule for all orders. This only applies to production orders and not MRP planned orders. |
From Date | Select the starting date for the schedule. The default is the current business date. |
To Date | Select the ending date for the schedule or leave this box blank. |
Schedule Details Table
The table displays the schedule details by date and time.
- Finitely scheduled production orders have assigned schedule blocks with a starting and ending date and time.
- Infinitely scheduled production orders and MRP planned orders are scheduled based on operation duration only and show starting and ending times of 11:59 PM.
The table shows the production order operations scheduled for each work center for the date range specified in the selection area. The schedule includes both infinite and finite planning blocks. The size of the blocks is defined in the Production Preferences (AM102000) form.
Column | Description |
---|---|
Work Center | The work center for the production or planned order operation. |
Shift | The shift scheduled for the production order operation. |
Plan Blocks | The number of blocks infinitely scheduled. |
Scheduled Blocks | The number of block finitely scheduled. |
Schedule Date | The starting date of the operation |
Start Time | For finite scheduled orders, the start time is calculated. |
End Time | The ending date for the operation based on the values in the Schedule Time and Start Time columns. |
Schedule Time | The duration of time expected for the operation to consume work center capacity. This value is the basis to determine how many scheduling blocks are consumed when the operation is scheduled. |
Break | A check box that indicates (if selected) that this time interval is a break time when operations cannot be scheduled. |
Description | The description of the break time. |
Order Type | This is the production order type. |
Production Nbr. | The production order number for the operation. |
Operation ID | The operation number of the production or planned order. |
Warehouse ID | This is the warehouse assigned to the production order. |
Resource Size | The crew size specified in the work center settings. |
Queue Time |
The time a semi-finished item has to wait in the work center before workers can start processing the item. |
Move Time |
The time for a semi-finished item to be moved from the work center where the current operation is performed to the work center where the next operation will be performed. |