Project AR Details
Form ID: (PM651002)
On this generic inquiry form, you can view the AR amounts—such as unbilled amounts, paid amounts, and unreleased retainage—for each listed document line. The system calculates these values as of the date you specify; you can also select a project and vendor to view only their document lines.
You can use the form to verify the AR amounts the system has calculated on the Project Cash Flow (PM651010) form.
Form Toolbar
The form toolbar has only standard buttons.
Selection Area
In this area, you select the date through which the system shows document lines in the table. By specifying a particular project or vendor (or both), you can narrow the range of document lines listed in the table.
| Element | Description |
|---|---|
| Date | The date through which the data is displayed—that is, you’ll see document lines up to and including this date. By default, the system inserts the current business date. |
| Project | The project for which you want to view the AR amounts. |
| Customer | The customer for which you want to view the AR amounts. |
Table
In the table, you can view the AR data for the selection criteria you’ve specified. You can use this information to verify the AR amounts that the system has calculated on the Project Cash Flow (PM651010) form. Each row represents a document line.
Below you’ll find descriptions of the columns that show information about the listed documents, their currency rates, and their calculated values, along with calculation formulas the system uses.
- The leftmost columns of the table aren't described in this topic. These columns display the document's basic information—such as company, branch, project, project task, account group, and cost code. If you need information about these UI elements, see their descriptions on the document's data entry form.
- The amounts are calculated in the project currency. The form shows values in the base, project, and document currencies if the Multicurrency Accounting and Multicurrency Projects features are enabled on the Enable/Disable Features (CS100000) form.
The table toolbar has only standard buttons.
| Column | Description |
|---|---|
| Date | The creation date of the document. |
| Record Type |
The type of the record, which is:
|
| Document Type | The specific type of the document, which is copied from the Type box of the Invoices and Memos (AR301000) or Payments and Applications (AR302000) form. |
| Ref. Nbr. | The reference number of the document created on the Invoices and Memos (AR301000) form or Payments and Applications (AR302000) form. |
| Line Nbr. | The line number of the document. |
| AR Document Type | The type of the AR document, such as Invoice, Debit Memo, Credit Memo, Overdue Charge, Credit WO, or Prepmt. Invoice. |
| AR Document Ref. Nbr. | The reference number of the AR invoice. |
| AR Document Line Nbr. | The line number of the AR document. |
| Base Currency | The base currency used for accounting in the branch associated with the project specified in this document line. |
| Document Currency | The currency of the document. |
| Customer | The customer specified in the AR invoice or payment. |
| Retainage Document | A check box that indicates (if selected) that the AR invoice is a retainage document: an invoice or memo that releases the retainage amount withheld from the original invoice. The system copies the state of the check box from the AR invoice on the Invoices and Memos (AR301000) form. |
| Rate (Project Curr.) | The rate used to convert document amounts to the project currency. The system uses the applicable rate on one of these dates:
|
| Rate (Base Curr.) | The rate used to convert document amounts to the base currency of the
project. The system uses the applicable rate on one of these dates:
|
| AR Document Qty. | The quantity specified in the line of the released AR invoice on the Invoices and Memos (AR301000) form:
|
| UOM | The unit of measure specified in the line of the invoice. |
| Unit Price (Project Curr.) | The price per UOM of the inventory item, which the system calculates by using
this formula: Extended Price (Project Curr.) / AR Document
Qty.Tip: This value is calculated in the project currency. If
multicurrency projects are set up in your system, you'll also see the
Unit Price (Base Curr.) column showing
the value in the base currency. The system calculates it similarly. |
| Extended Price | The extended price specified in the line of the released AR invoice on the
Invoices and Memos (AR301000) form:
|
| Extended Price (Project Curr.) | The extended price specified in the line of the released AR invoice, which the
system calculates by using this formula: Extended Price * Rate (Project
Curr.)Tip: This value is calculated in the project currency.
If multicurrency projects are set up in your system, you'll also see the
Extended Price (Base Curr.) column showing the value in
the base currency. The system calculates it similarly. |
| Inclusive Taxes on AR (Project Curr.) | The tax amount applied to the project's AR invoice, which the system
proportionally spreads across the lines of the invoice with the tax category that
requires this tax calculation. For a document of the Credit Memo type, the amount is shown as a negative value. Tip: This value is calculated
in the project currency. If multicurrency projects are set up in your system,
you'll also see the Inclusive Taxes on AR (Base Curr.)
column showing the value in the base currency. The system calculates it
similarly. |
| Exclusive Taxes on AR (Project Curr.) | The tax amount on the amount of the AR, which the system calculates by using
this formula: (Amount Paid + Cash Discount Taken) * Billed Tax (Project
Curr.) of each paid bill line / Amount of the paid bill.
Tip: This value is calculated in the project currency. If
multicurrency projects are set up in your system, you'll also see the
Exclusive Taxes on AR (Base Curr.) column. showing the
value in the base currency. The system calculates it similarly. |
| AR Retained Amount (Project Curr.) | The retainage amount specified in the AR invoice, which the system calculates
by using one of these formulas depending on the type of the document:
Tip: This value is calculated in the project currency. If
multicurrency projects are set up in your system, you'll also see the
AR Retained Amount (Base Curr.) column showing the value
in the base currency. The system calculates it similarly. |
| AR Retained Taxes (Project Curr.) | The retained tax amount applied to the project's AR invoice and credit memos,
which the system proportionally spreads across the lines of the AR invoice. For a document of the Credit Memo type, the amount is shown as a negative value. Tip: This value is calculated in the project currency. If
multicurrency projects are set up in your system, you'll also see the
AR Retained Taxes (Base Curr.) column showing the value
in the base currency. The system calculates it similarly. |
| AR Amount | The amount specified in the lines of the released AR invoice, which the system
calculates by using this formula: AR Amount = SUM of Amount values +
Inclusive Taxes on AR (Project Curr.).For a document of the Credit Memo type, the amount is shown as a negative value. |
| AR Amount (Project Curr.) | The amount specified in the released AR invoice, which the system calculates by
using this formula: AR Amount / Rate (Project Curr.).If the project currency is the same as the document currency, this value is the same as the AR Amount. If the project currency is the same as the document’s base currency, the system multiplies the AR Amount by the base currency rate specified on the Invoices and Memos (AR301000) form. Tip: This value is
calculated in the project currency. If multicurrency projects are set up in your
system, you'll also see the AR Amount (Base Curr.) column
showing the value in the base currency. The system calculates it
similarly. |
| AR Paid Amount | The paid amount specified in the AR invoice, which can be one of the following,
depending on the state of the Pay by Line check box on the
Invoices and Memos (AR301000) form:
|
| AR Paid Amount (Project Curr.) | The paid amount specified in the AR invoice, which the system calculates by
using this formula: AR Paid Amount * Rate (Project Curr.).Tip: This value is calculated in the project currency. If multicurrency
projects are set up in your system, you'll also see the AR Paid Amount
(Base Curr.) column showing the value in the base currency. The
system calculates it similarly. |
| AR Cash Discount (Project Curr.) | The AR cash discount, which can be either of the following, depending on the
state of the Pay by Line check box on the Invoices and Memos (AR301000) form:
Tip: This value is calculated in the project currency. If
multicurrency projects are set up in your system, you'll also see the
AR Cash Discount (Base Curr.) column showing the value in
the base currency. The system calculates it similarly. |
| Write-Off Amount (Project Curr.) | The write-off amount, which can be either of the following, depending on the
state of the Pay by Line check box on the Invoices and Memos (AR301000) form:
Tip: This value is calculated in the project currency. If
multicurrency projects are set up in your system, you'll also see the
Write-Off Amount (Base Curr.) column showing the value in
the base currency. The system calculates it similarly. |
| Paid Inclusive Tax (Project Curr.) | The paid inclusive tax amount, which the system calculates by using this
formula: (Amount Paid + Cash Discount Taken) * Inclusive Taxes on AR
(Project Curr.) of each paid AR invoice line / Amount of the paid
invoice.
Tip: This value is calculated in the project currency. If
multicurrency projects are set up in your system, you'll also see the
Paid Inclusive Tax (Base Curr.) column showing the value
in the base currency. The system calculates it similarly. |
| Exclusive Taxes on Paid AR (Project Curr.) | The tax amount on the paid amount of the invoice, which the system calculates
by using this formula: (Amount Paid + Cash Discount Taken) * Exclusive Taxes
on AR (Project Curr.) of each paid invoice line / Amount of the paid
invoice.
Tip: This value is calculated in the project currency. If
multicurrency projects are set up in your system, you'll also see the
Exclusive Taxes on Paid AR (Base Curr.) column showing
the value in the base currency. The system calculates it similarly. |
| Realized Gain/Loss (Project Curr.) | The realized gain or loss, which the system calculates by using this formula:
AR Paid Amount * Rate (Project Curr.) on the original invoice's date -
Rate (Project Curr.) on the payment date.If the project currency is the same as the AR invoice's currency, the realized gain or loss is 0. If the project currency is the same as the AR invoice's base currency, the realized gain or loss is the same as the one specified in the GL transaction. Tip: This value is calculated in the project currency.
If multicurrency projects are set up in your system, you'll also see the
Realized Gain/Loss (Base Curr.) column showing the value
in the base currency. The system calculates it similarly. |