Change Requests: To Process Cost-Only Changes to a Project
The following activity will walk you through the process of managing changes to the construction project by using the two-tier change management workflow.
Story
Suppose that ToadGreen is a general contractor building an Italian restaurant for the Italian Company, its customer. The ToadGreen project manager has created a project for the work to be performed, and the budget has been agreed upon with the customer. The construction work has been started. Further suppose that on March, 21, 2024, an on-site worker found out that the wet subfloor in the building needs to be dried, cleaned, and aired out, and this worker has notified the project manager about this.
After reviewing the damages, the project manager has decided to hire a subcontractor, Acme Doors & Glass, to perform this work. The subcontractor notifies the project manager that four working days are needed for completing the cleaning. The customer for which the project is being performed did not approved the changes because the damages were the workers' fault.
Acting as the project manager, you need to reflect the additional work in the cost project budget and cancel the changes in the revenue budget.
Configuration Overview
In the U100 dataset, the following tasks have been performed for the purposes of this activity:
- On the Enable/Disable Features (CS100000) form, the Construction and Change Orders features have been enabled.
- On the Account Groups (PM201000) form, the REVENUE account group has been configured.
- On the Projects (PM301000) form, the ITALIAN project has been configured; the project tasks have been created, along with the related cost and revenue budget.
Process Overview
You will create a change request on the Change Requests (PM308500) form. After that, you will create a change order for this change request on the Change Orders (PM308000) form and add commitments to this change order. Then you will make sure that the processed documents are correctly reflected in the cost budget of the project. Finally, you will manually close the change request on the Change Requests form to indicate that revenue part does not require processing.
System Preparation
To prepare to perform the instructions of this activity, do the following:
- As a prerequisite activity, complete the Change Requests: To Configure Project Markups to define the markups for the project.
- Sign in to a company with the U100 dataset preloaded. You should sign in as project manager by using the ewatson username and the 123 password.
- In the info area, in the upper-right corner of the top pane of the MYOB Acumatica screen, make sure that the business date in your system is set to 3/21/2024. If a different date is displayed, click the Business Date menu button, and select 3/21/2024 on the calendar. For simplicity, in this activity, you will create and process all documents in the system on this business date.
Step 1: Creating a Change Request
Create the change request that records the planned work to be performed as follows:
- On the Change Requests (PM308500) form, create a new change request, and
specify the following settings in the Summary area:
- Project: ITALIAN
- Change Date: 3/21/2024
- Contract Time Change, Days: 4
- Description: Work on wet subfloor
- On the Detailed Description tab, type Wet subfloor needs to be dried, cleaned, and aired out.
- On the Estimation tab, add a line with the following settings:
- Project Task: 01
- Account Group: LABOR
- Cost Code: 01-900
- Quantity: 1
- UOM: EA
- Unit Cost: 1000
- Price Markup (%): 10
- Revenue Task: 01
- Revenue Account Group: REVENUE
- Revenue Code: 01-000
- Add one more line with the following settings:
- Project Task: 03
- Account Group: SUBCON
- Cost Code: 03-350
- Quantity: 10
- UOM: HOUR
- Unit Cost: 38
- Price Markup (%): 10
- Revenue Task: 03
- Revenue Account Group: REVENUE
- Revenue Code: 03-000
- Vendor: SUNTECH
- Create Commitment: Selected
- In the Summary area, make sure that the Cost Total is 1380.
- Save the change request.
- On the form toolbar, click Remove Hold. The change request now
has the Open status.Tip: In production use, you can configure an approval map for change requests and specify it in the Change Request Approval Map box on the Approval tab of the Projects Preferences (PM101000) form, so that the responsible person will need to approve the change request before it is assigned the Open status.
Step 2: Processing the Change Order
To create and process a change order, do the following:
- On the Change Orders (PM308000) form, create a new record.
- In the Class box, select INTERNAL. This is the class of change orders that is used for processing the cost part of the changes.
- In the Project box, select ITALIAN.
- In the Description box in the Summary area, type Additional costs for the Italian Restaurant.
- On the table toolbar of the Change Requests tab, click Select Change Requests.
- In the Select Change Requests dialog box, which opens, select the unlabeled check box in the row of the change request that you created earlier (Work on wet subfloor), and then click Add Change Requests & Close. The system adds the line with the change request to the table on the Change Requests tab and specifies the cost budget and commitment details on the Cost Budget tab and the Commitments tab, respectively. The change request still has the Open status because the revenue part of this change request has not yet been processed.
- On the Cost Budget tab, make sure that the cost budget lines with the 01-900 and 03-350 cost codes have been added.
- On the Commitments tab, make sure that the potential commitment with the amount of $380 has been added for the change order. The line has New Document in the Status column, which means that a new document will be prepared when the change order is released.
- In the Commitment Type column of the only line on the Commitments tab, change the type of the commitment to be prepared to Subcontract.
- On the form toolbar, click Remove Hold. The system saves the change order and assigns it the Open status.
- On the form toolbar, click Release to release the change order.
Step 3: Reviewing the Project Budget
Make sure that the change order has updated the project budget by doing the following:
- On the Projects (PM301000) form, open the ITALIAN project.
- On the Cost Budget tab, review the amounts in the budget lines, and notice that they have been moved from the Potential CO Amount column to the Budgeted CO Amount column, and the system has also updated the amounts in the Revised Budgeted Amount column.
- On the Revenue Budget tab, review the amounts in the budget lines with the 01-000 02-000, and 03-000 cost codes, and notice that the change request values are still included in the potential values.
Step 4: Closing the Change Request
To clean up the potential values in the revenue budget of the project, while you are still reviewing the project on the Projects (PM301000) form, do the following:
- On the Change Requests tab, click the link in the Reference Nbr. column of the only row.
- On the form toolbar of the Change Requests (PM308500) form, which opens in a pop-up window, click Close. The system assigns the change request the Closed status.
- Close the pop-up window, and return to the ITALIAN project on the Projects form. Press Esc to refresh the form.
- On the Revenue Budget tab, review the amounts in the budget lines with the 01-000, 02-000, and 03-000 cost codes, and notice that the potential value in both lines has been decreased to 0.
You have completed the processing of a change order and processed the cost part of the change request for the project.