Requests for Information: Mass-Processing of Documents
The following section explains how to mass-assign owners to requests for information.
Mass-Assigning Owners to Project Issues
You use the Assign Request for Information (PJ501000) form to assign owners to requests for information. To do this, you select the check boxes in the unlabeled column for the requests for information that you want to assign to owners and then click Process on the form toolbar. If you want to assign owners to all requests for information, click Process All.
The system assigns owners according to the assignment map selected in the RFI Assignment Map box of the Project Management Preferences (PJ101000) form.