Contract Management: Contract Upgrade Process

Before the setup and activation of a contract created on the Customer Contracts (CT301000) form, the contract has the Draft status, and you can make any needed changes.

After contract setup and activation, you can make only limited changes to the contract. To begin making these changes, if the contract has the Active status, you start the upgrade process by clicking Upgrade Contract on the More menu. This changes the status of the contract to Pending Upgrade and gives you the ability to make allowable changes to the contract.

Once you have finished making the needed changes to the contract, you click Activate Upgrade on the More menu (under Processing).

Permissible Changes During Contract Upgrade

Not all elements of the Customer Contracts (CT301000) form can be changed during a contract upgrade. In the Summary area of the form, you can select a different customer location or modify the description of the contract. These changes can be done for a contract with the Active status without the upgrade procedure.

On the Summary tab, you can change most settings in the Contract Settings and Contract Management sections. None of the settings in the Billing Schedule section can be changed, and in the Billing Information section, you can change only the option selected in the Bill To box.

On the Details tab, you can change the effective date of the upgrade and apply a new discount code. Also, in the table of the tab, you can change the set of included contract items and change their quantities within allowable limits. Note that you can change the set of provided contract items only if for the template the contract is based on, the Enable Template Item Override check box is selected on the Contract Templates (CT202000) form.

Contract Billing and Provisioning of an Upgraded Contract