Story

Suppose that the ToadGreen Building Group company is building a hotel for the Equity Group Investors customer. The ToadGreen project manager has created a project to track the work progress and to control related revenues and expenses. In April and May 2023, the project accountant has prepared two pro forma invoices, each for part of the performed work; after the customer agreed to the amounts, the project accountant billed the customer.

Further suppose that at the end of May, the ToadGreen construction project manager noticed that a mistake had been made in two lines of the first pro forma invoice. The total of the pro forma invoice is 10,806,560.21, but it should be 10,601,350.41. The construction project manager has reviewed the invoice details and found out that the following corrections must be made:

  • The Amount to Invoice in the line with the 03 project task and 03-000 cost code is 5,990,284.80, but it should be 5,783,075.00.
  • The Amount to Invoice in the line with the 04 project task and 04-000 cost code is 145,277.76, but it should be 147,277.76.

The incorrect pro forma invoice was already used for generating the March AIA report. Because the amounts in the first AIA report were incorrect, the April report also needs to be corrected and the AIA report has to be generated again.

Acting as the construction project manager, you need to enter and process the related documents to adjust the actual amounts in AIA reports for March and for April. You then need to regenerate these AIA reports.

Configuration Overview

In the U100 dataset, the following tasks have been performed for the purposes of this activity:

  • On the Enable/Disable Features (CS100000) form, the following features have been enabled:
    • Project Accounting, which provides support for the project accounting functionality
    • Construction, which gives you the ability to make corrections to pro forma invoices with the corresponding AR document released
  • On the Projects (PM301000) form, the HOTELSM project has been created with multiple project tasks, including the 03 and 04 project tasks. Also, on the Cost Budgets tab, the cost budget is defined for the line with the 03-000 and 04-000 cost codes.
  • On the Pro Forma Invoices (PM307000) form, a pro forma invoice dated 4/1/2023 has been created for the project and released. On the Invoices and Memos (AR301000) form, the accounts receivable invoice corresponding to the pro forma invoice has been created and released.
  • On the Pro Forma Invoices form, a pro forma invoice dated 5/1/2023 has been created for the project and released. On the Invoices and Memos form, the accounts receivable invoice corresponding to the pro forma invoice has been created and released.

Process Overview

In this activity, on the Pro Forma Invoices (PM307000) form, you will initiate the correcting of a pro forma invoice for the project. You will adjust the amounts and release the corrected pro forma invoice. On the Invoices and Memos (AR301000) form, you will release the accounts receivable invoice created based on the pro forma invoice and the credit memo created to reverse the previous AR invoice. Finally, you will regenerate the AIA report for the corrected pro forma invoice and for the subsequent one; you will open the regenerated AIA reports on the AIA Report (PM644000) form to verify that the amounts are correct.

System Preparation

To prepare to perform the instructions of this activity, do the following:

  1. Launch the MYOB Advanced website, and sign in to a company with the U100 dataset preloaded. You should sign in as a construction project manager by using the ewatson username and the 123 password.
  2. In the info area, in the upper-right corner of the top pane of the MYOB Advanced screen, make sure that the business date in your system is set to 5/29/2023. If a different date is displayed, click the Business Date menu button, and select 5/29/2023 on the calendar. For simplicity, in this activity, you will create and process all documents in the system on this business date.

Step 1: Correcting the Pro Forma Invoice

To correct the pro forma invoice for the project, do the following:

  1. On the Projects (PM301000) form, open the HOTELSM project.

    On the Invoices tab, review the pro forma invoices and accounts receivable invoices generated for the project. Notice that the status of both pro forma invoices is Closed and the status of both accounts receivable invoices is Open because the AR invoices have been generated for the pro forma invoices and released.

  2. Click the Pro Forma Reference Nbr. link in the first line to open the pro forma invoice on the Pro Forma Invoices (PM307000) form. You need to correct the amounts in the lines with the 03 project task and 03-000 cost code and 04 project task and 04-000 cost code.
  3. On the More menu, click Correct to make corrections to the pro forma invoice. The system assigns the pro forma invoice the On Hold status. Make sure that the Invoice Date is the date of the original accounts receivable invoice (4/1/2023).

    On the Financial tab, notice that the AR Ref. Nbr. box (Invoice Settings section) is empty (because this pro forma invoice is being edited and has not been released) and a row with the previous revision of the accounts receivable invoice (which has an invoice total of $10,806,560.21) has appeared in the Previous Revisions table.

  4. On the Progress Billing tab, correct the amounts in the Amount to Invoice column as follows:
    • In the lines with the 01 and 02 project tasks, leave the existing amounts.
    • In the line with the 03 project task, enter 5,783,075.00.
    • In the line with the 04 project task, enter 147,277.76.
  5. In the Summary area, make sure that the invoice total is now 10,601,350.41.
  6. On the form toolbar, click Remove Hold, and then click Release to release the pro forma invoice. The system creates the accounts receivable invoice based on the pro forma invoice and assigns the Closed status to the pro forma invoice.

    In the Previous Revisions table of the Financial tab, in the line for the previous revision of the AR invoice, notice that a reference number is now shown in the Reversing Ref. Nbr. column. This is the number of the credit memo the system has created to reverse this AR invoice.

  7. Click the Edit button to the right of the AR Ref. Nbr. box (Invoice Settings section) to open the accounts receivable invoice that was created when you released the corrected pro forma invoice.
  8. On the form toolbar of the Invoices and Memos (AR301000) form, which the system opens in a pop-up window, click Remove Hold, and then click Release to release the accounts receivable invoice.

Step 2: Regenerating AIA Reports

  1. On the Projects form, open the HOTELSM project.

    On the Invoices tab, notice that the corrected AR invoice and the correction credit memo have appeared in the table. Also, notice the warnings indicating that the AIA reports have to be regenerated for the pro forma invoices because the amounts have changed.

  2. Click the first line in the table, and on the table toolbar, click AIA Report to again generate the AIA report for April. The system generates the AIA report and opens it on the AIA Report (PM644000) form. In the Continuation Sheet of the report, make sure the last two lines show the updated amounts, as shown in the following screenshot.
    Figure 1. Corrected amounts in AIA report


  3. Click Back in the browser tab to return to the HOTELSM project on the Projects form. On the Invoices tab, notice that the warning is now shown only for the pro forma invoice dated 5/1/2023.
  4. Click the line with this invoice in the table, and on the table toolbar, click AIA Report to again generate the AIA report for May. The system generates the updated AIA report and opens it on the AIA Report (PM644000) form. Make sure that Total Completed & Stored to Date has been updated and now equals 12,602,270.04.

You have finished correcting the amounts in the pro forma invoice and prepared updated AIA reports. In a production setting, project accountant would apply the reversing credit memo to the original AR invoice, which is beyond the scope of this activity.