MRP Configuration: Variable Manufacturing Lead Times

When the system calculates demand for materials used in production on the Regenerate MRP (AM505000) form, the system creates planning orders for materials that must be produced. For each planning order, the system specifies an action date, which is the date when the production must start. To calculate the action dates, the system calculates the lead times required to produce the needed quantity of materials. The variable manufacturing lead time depends on the quantity of produced items in production orders for which material requirements planning (MRP) is performed. This lead lime consists of lead times of operations in bills of material that provide the production routing for the materials. You specify the settings that determine the operation lead times on the Bill of Material (AM208000) form.

In the following sections, you can find details about the variable manufacturing lead times.

Components of the Variable Manufacturing Lead Time

For each operation of a bill of material, you specify the settings that determine variable lead times in the Operations table of the Bill of Material (AM208000) form. The system uses the following components of operation lead times during calculation of action dates of planning orders for materials to be produced:

  • Worker throughput: The quantity of item units produced during a certain period of time when machines are not involved in the operation. The system determines that machines are not involved when Crew Size is selected in the Basis for Capacity box on the Work Centers (AM207000) form for the work center specified in the operation row. In the Run Time column of the row, you specify the period of time (such as 01:00 for one hour), and in the Run Units column, you specify the quantity of item units that workers produce during this period of time (such as 5).
  • Machine throughput: The quantity of item units produced during a certain period of time when machines are used in the operation. The system determines that machines are involved when Machines is selected in the Basis for Capacity box on the Work Centers form for the work center specified in the operation row. In the Machine Time column of the row, you specify the period of time, and in the Machine Units column, you specify the quantity of item units that workers produce during this period of time by using the machine.
  • Setup time: The time it takes to prepare to start the operation, which is specified in the Setup Time column of the operation row. For example, to prepare for the operation, workers may need to print drawings or take parts from a stock room. Based on this value, the system adds a fixed labor cost to the cost of the produced item, regardless of the size of the order.
Important: The following components that also determine variable manufacturing lead time are not considered during the calculation of action dates for planning orders in MRP:
  • Queue time, move time, and finish time, which you specify in the Operations table of the Bill of Material (AM208000) form
  • Work center capacity, which is calculated as Crew Size * Efficiency, where crew size and efficiency are specified on the Shifts tab of the Work Centers (AM207000) form)

Configuration of Variable Manufacturing Lead Time

You configure the variable manufacturing lead time to be used in material requirements planning as follows:

  1. On the Work Centers (AM207000) form, you specify the following settings for each work center that will be specified in an operation of the bill of material:
    • In the Basis for Capacity box on the General tab, you specify which throughput settings (run units and time, or machine units and time) the system will use for operations in this work center.
    • In the Calendar ID column on the Shifts tab, you specify the work calendar the system will use for calculating lead times for operations performed in this work center.
  2. If machines are used in any work center, on the Machines (AM204500) form, make sure that the calendar specified for each machine has the same working hours as the work center to which the machine is assigned.
  3. On the Bill of Material (AM208000) form, in the Operations table, you specify the lead time components for each operation when creating a bill of material.

Calculation of the Manufacturing Lead Time

When calculating action dates for planning orders, the system calculates the time required for performing each operation in the routing by using one of the following formulas (depending on whether run time or machine time is used).

Setup Time + (Qty. to Produce * (Run Time / Run Units))
Setup Time + (Qty. to Produce * (Machine Time / Machine Units))

If the value of Run Units or Machine Units is 0, then the parts of the formula that include the units are 0.

For example, suppose that a bill of material for producing wooden chairs includes two operations with the settings specified in the following table. The throughput for the paint operation is one chair per hour, and the throughput for the assembly operation is five chairs per hour.

Operation Setup Time Run Units Run Time
Paint 01:00 1 01:00
Assembly 00:00 5 01:00

Also suppose that the work centers where the operations take place have an 8-hour working day and Saturday and Sunday as non-working days. Further suppose that a sales manager created a sales order for the production of 10 chairs with the customer requiring the order by January 30 (which is a working day). A production manager runs material requirements planning to receive the list of planning orders to meet the date when the customer requires the chairs. To produce 10 chairs, it will take 11 hours for the paint operation and 2 hours for the assembly operation—13 hours in total. If the production must end on January 30, then the start date of the planned order for production will be January 29 if it is a working day according to the work calendar.