Material Requirement Planning
Material Requirements Planning (MRP) combines a sales forecast and sales
orders with bill of material and inventory data to calculate what materials
are required, and when they are required, to satisfy customer requirements.
The process determines material requirements, including all components
in a bill of material, using the date of the forecast or sales order for
the finished product. The process considers inventory on-hand and on-order
balances, minimum balances, supplier and manufacturing lead times, and
the like.
Time phased MRP
- All processing is date specific.
- Supplier and manufacturing lead times are considered when calculating
order requirement and inventory availability dates.
Four demand generation options
Use these options as input to the MRP process to generate demand:
- Forecast only.
- Sales orders consume forecast.
- Sales orders plus forecast.
- Sales orders only.
Multiple versions of MRP or Forecast
You can process What
if scenarios by combining different forecast file names with different
MRP file names.
Demand time fence
- This represents the time in which Greentree Desktop
only considers sales orders, regardless of the demand generation option.
- This is useful when running MRP near the end of a month when all
sales orders for that month have been entered. By entering a month
end date, the process only considers sales orders.
Critical Items
- You can flag inventory items, including manufacturing components,
as critical items.
- You can use critical items to restrict the number of items included
in calculations, so that potential supply problems can be quickly
highlighted.
- A critical item can be any inventory item, but would include items
with a long lead time, a high value, or one that is particularly critical
to the manufacturing process.
Planned orders
- You can generate factory and purchase orders based on system calculated
planned orders, generated using the MRP process.
- You can combine orders.
- Generated orders do not depend on supplier or re-order details
being set up.
Action messages
Action messages are system generated to notify requirements to expedite,
de-expedite or cancel existing orders.
Kitsets
Kitset parent and component items are included in the MRP process.
Forecast
The Manufacturing Forecasting sub module generates the forecasts used
as input to the MRP process.
Exclusions
These functions are not included in the MRP sub module:
- MRP by warehouse.
- Capacity planning.
- Factory Calendar.
- SO-PO and SO-FO linking are not considered in the process, for
example, a sales order linked to a purchase order will not prevent
the purchase order from being rescheduled if there is a requirement
from another sales order or forecast.