MRP Tab
This tab is enabled if the Material Requirements Planning sub module is in use.
Use this tab to specify controls associated with the MRP process.
Options Reference
Each option and field on the form is described below. Mandatory options and fields are highlighted in red.
Demand Generation
Select the option to use for generating demand, used as input to the MRP process:
- Forecast only - This option
is enabled if the Forecasting module is in use.
If you select this option, Greentree Desktop only uses the forecast to determine requirements.
- Sales orders consume forecast
- This option is enabled if the Forecasting module is in use.
If you select this option, the process takes sales orders into account when determining requirements, but the orders consume the forecasted quantity.
- Sales orders plus forecast
- This option is enabled if the Forecasting module is in use.
If you select this option, the process adds sales orders to the forecast when determining requirements.
- Sales orders only - Greentree Desktop ignores
the forecast and use only sales orders to determine requirements.
Note: This is the default setting when you create a company. It is the only option you can select if the Forecasting module is not in use.
Here are some examples:
Demand Generation Method |
Forecast |
Sales Orders |
Gross Requirements |
Forecast |
10.00 |
6.00 |
10.00 |
Sales orders consume forecast |
10.00 |
6.00 |
10.00 (6 relate to sales orders + 4 remaining forecasted) |
Sales orders plus forecast |
10.00 |
6.00 |
16.00 |
Sales orders only |
10.00 |
6.00 |
6.00 |
Exclude Hold and don't commit orders
Select this option to exclude sales orders with a Hold and don't commit status when calculating requirements.
Create planned orders for purchasing first
Select this option to generate planned purchase orders for manufactured items with a bill of material, instead of planned factory orders, when the MRP process runs.
If you select this option, requirements for components in the bill of material are excluded from the MRP generation process, and planned orders for components are not created. If the option is not selected, planned factory orders is created, and requirements for bill of material components is included in the MRP generation process.
Default FO location
This is the default location the MRP Generation process references when planned factory orders are created.
Default PO location
This is the default location that the MRP Generation process references when planned purchase orders are created. The location is also used to determine inventory item supplier details. If there are no active supplier details for this location, the planned order is created with a empty supplier.
- Material Requirements Planning
- Forecasting
- Calculations - Forecast Only
- Calculations - Sales Orders Consume Forecast
- Calculations - Sales Orders Plus Forecast
- Calculations - Sales Orders Only
- MRP Generation