<p>You use this form to roll up the costs of bills of material (BOMs) based on the costs of the entities included in the BOMs, such as labor or materials. The system includes the costs of subassemblies in the material costs of the parent BOMs. You can also update the pending standard costs of items assigned to BOMs and subassemblies used as materials.</p>[2]<p>You use this form to roll up the costs of bill.. 2023/05/0509:40:17-04:00 [3]insert2023/05/0421:24:07-04:00- Roll up the costs of bills of material (BOMs) based on the costs of the entities included in the BOMs, such as labor or material.
- Update material costs on bills of materials.
- Use the roll up cost of subassemblies for the parent BOM cost calculation.
- Use the current item valuation for the cost roll process.
- Use the roll up cost to update the pending standard cost of stock items whose item valuation method is Standard. For more information, see Bills of Material: Updating Standard Costs.
- A warehouse is specified in the Warehouse box on the Bill of Material (AM208000) form.
- A record for the item–warehouse pair exists on the Item Warehouse Details form.
- The Override Std. Cost check box is selected on the Price/Cost tab of the Item Warehouse Details form.
On this form, you can also archive the results of the cost rollup process.
Form Toolbar
The form toolbar includes standard and form-specific buttons and commands. For the list of standard buttons, see Form Toolbar and More Menu. The form-specific commands are listed in the following table.
| Command | Description |
|---|---|
| Archive |
Archives the results of the cost calculation to the Cost Roll History (AM408000) form. You can archive the results after the cost rollup process. If the [5]At minimum, "Without" should be capped (prepositions of more than four letters are always capped), but the name is problematic because the last three words seem to be saying "if an update is not pending," but that is not correct. Here and in the command name, we are missing the object of the verb, Costs. For clarity, it should say "Allow Archive Without Updating Pending Costs." I know this is longer, but it actually makes sense and says what we mean.u5k_cj1_w5b2022/09/1320:34:45-04:00Keep for renaming7u5k_cj1_w5b72022/09/1414:39:30+03:00Allow Archive without Update Pending check box is selected on the BOM Preferences (AM101000) form, you can archive the cost rollup results without updating the pending costs. If the check box is cleared, you must update pending costs first by clicking Update Pending. The system archives BOM records for the current date. If you archive the results multiple times on the same date, the system overrides the previous data for this date. |
| [6]Should be called "Roll Up Costs" (here, "up" is functioning as an adverb, so it should be capped). Rolling costs means something different, although I have no idea what it could be.y2d_qj1_w5b2022/09/1318:03:51-04:00Keep for renaming5y2d_qj1_w5b52022/09/1414:43:31+03:00Roll Costs | Rolls up the cost of the bills of material that meet the criteria in the Selection area. If no criteria are specified, the system rolls up the costs for all bills of material. |
| [7]This name also needs to be changed. It does not sound like what it means. It sounds like it means that an update is pending (awaiting something), because we have peeled off the object. The object is essential to convey the meaning. It should say Update Pending Costs.e2j_wj1_w5b2022/09/1317:45:37-04:00Keep for renaming7e2j_wj1_w5b72022/09/1414:45:20+03:00Update Pending |
Updates the pending costs of the stock items assigned to the BOMs for which costs have been rolled up with the calculated costs. [8]insert2023/05/0421:31:29-04:00This is only applicable for items with the Standard valuation method. The pending costs are updated for items with any valuation method.[9]The pending costs are updated for items with any .. 2023/05/0421:32:02-04:00 The system finds the items based on the value in the Default BOM ID box on the Stock Items (IN202500) or Item Warehouse Details (IN204500) form [10] 2023/05/0514:50:59-04:00. If the [11]The name of this element is really not good. There are a couple problems: It should be "Auto-Archive" rather than "Auto Archive" (but I argue that we don't need auto at all; archival is always something done by the system, so the word is adding no corresponding increase in understanding--just "Archive" is absolutely fine), and "when Update Pending"does not compute. It sounds like shorthand for "when an update is pending" but that is not actually what we mean. We mean, as this seems to be saying, "when the system is updating pending costs." Of course, that is very lengthy! I would call it "Archive on Pending Cost Update". It's two characters shorter (so no real gain there) but the meaning is clear.x4m_zk1_w5b2022/09/1315:40:17-04:00Keep for renaming9x4m_zk1_w5b92022/09/1414:53:52+03:00Auto Archive when Update Pending check box is selected on the BOM Preferences (AM101000) form, the system archives the cost rollup results after updating the pending costs. The results are archived for stock items with any valuation method. For details about updating standard costs for items to be produced, see Bills of Material: Updating Standard Costs. |
Selection Area
Some of the elements in this area limit the bills of material that are processed when you run cost rollup. For example, you may want to roll up costs for items in a particular warehouse or assigned to a particular item class. You can also specify whether the system should roll up costs for subassemblies included in BOMs or use the cost specified for each subassembly on the Materials tab of the Bill of Material (AM208000) form.
[12]- I am very surprised that it works this way. So the reader is "blind" to which specific BOMs will be included prior to the processing? And how will the states of the Included check boxes affect the included BOMs ... or won't they? - Change the end of this to be very specific that the selection criteria are used only when the __ [command is or commands are] clicked.kgz_nl1_w5b2022/09/1320:21:26-04:00This need to be tested first.11kgz_nl1_w5b112022/09/1414:58:07+03:00| Element | Description |
|---|---|
| Level |
The depth of cost calculation, which indicates whether the system should calculate costs for included subassemblies. You can select either of the following options:
|
| Item Class |
The item class assigned to the stock items whose costs you would like to roll up. If Multi is selected in the Level box and the BOM assigned to an item of the class includes subassemblies, the system will calculate costs of the related subassemblies with any item class. |
| Warehouse | The warehouse assigned to bills of material for which you costs will be rolled up. |
| Inventory ID |
The identifier of the stock item for which costs will be rolled up. If Multi is selected in the Level box and the bill of material assigned to the item includes subassemblies, the system will calculate costs for the subassemblies and list the subassembly records in the table. |
| Subitem |
The subitem of the inventory item for which costs will be rolled up. This column is visible only if the Inventory
Subitems feature is enabled on the Enable/Disable Features
(CS100000) form.
Important: The Inventory
Subitems check box has been removed from the Enable/Disable Features (CS100000) form because the functionality
associated with the Inventory Subitems feature will be phased out. If you have
this feature enabled in your system, the associated functionality remains available. To
disable the feature, contact your MYOB support provider. |
| BOM ID |
The bill of material for which costs will be rolled up. If Multi is selected in the Level box and the BOM includes subassemblies, the system will calculate costs for the subassemblies and list the subassembly records in the table. |
| Revision | The revision of the BOM specified in the BOM ID box for which costs will be rolled up. |
| Effective Date |
The effective date of the pending cost, which the system will copy to the Pending Cost Date box of the Price/Cost tab on the Stock Items (IN202500) or Item Warehouse Details (IN204500) form. This setting is required if you will apply the rolled up costs to pending costs by clicking the Update Pending button. |
| Include Material Scrap Factors | A check box that you select if [13]insert2023/05/0421:32:53-04:00the system should consider the scrap factor specified for materials on the Materials tab of the Bill of Material (AM208000) during the cost roll process.when rolling up the BOM costs, the system should consider the scrap factor specified for materials on the <uicontrol>Materials</uicontrol> tab of the <xref href="AM_20_80_00.dita"/> (AM208000) form.[14]when rolling up the BOM costs, the system should .. 2023/05/0421:33:21-04:00 |
| Include Fixed Costs | A check box that you select if the system should include all fixed costs (such as the setup time of an operation or fixed overhead costs) in the BOM cost. |
| Update Material |
A check box that you select if the system should update the unit costs of the materials used in the BOMs during the cost rollup. <p>During the update, the system copies the material cost from the <uicontrol>Price/Cost</uicontrol> tab of the <xref href="IN_20_25_00.dita"/> or <xref href="IN_20_45_00.dita"/> form to the <uicontrol>Unit Cost</uicontrol> column of the <uicontrol>Materials</uicontrol> tab on the <xref href="AM_20_80_00.dita"/> form depending on the valuation method of the material as follows:</p><ul id="_1d283f7d-f7f3-4efa-8a48-5176d3d38b35"><li><i>Standard</i>: The current standard cost</li><li><i>Average</i> or <i>FIFO</i>: The average cost</li><li><i>Specific</i>: The last cost</li></ul>[15]<p>During the update, the system copies the mater.. 2023/05/0813:25:15-04:00 |
| Use Pending Standard for [16]Please report that this should be changed to "Purchased" ... "purchase items" is only a verb phrase and is not what we mean here.2022/09/1315:46:09-04:00Purchase Items | A this[17]this2023/05/0421:34:28-04:00 check box that you select if the system should use the pending standard cost instead of the standard cost for purchased items when rolling up costs. This check box applies to only items with a valuation method of Standard. |
| [18]I'm not sure about this setting, need to ask SMEs.2022/09/0618:54:05+03:00Ignore Min/Max/Lot Size Values | A check box that you select if the system should ignore the Min Order Qty., Max Order Qty., and Lot Size settings on the Manufacturing tab of the Stock Items (IN202500) or Item Warehouse Details (IN204500) form when calculating fixed costs (such as labor or overhead costs) during the cost rollup. |
Table
The table lists the bills of material for which the system has rolled up costs.
The table toolbar includes only standard buttons. For the list of standard buttons, see Table Toolbar.
| Column | Description |
|---|---|
| BOM ID | The bill of material whose cost has been rolled up. |
| Revision | The revision of the bill of material specified in the BOM ID column. |
| Warehouse | The warehouse assigned to the BOM. |
| Inventory ID | The stock item assigned to the BOM. |
| Subitem |
The subitem of the inventory item. This column is visible only if the Inventory
Subitems feature is enabled on the Enable/Disable Features
(CS100000) form.
Important: The Inventory
Subitems check box has been removed from the Enable/Disable Features (CS100000) form because the functionality
associated with the Inventory Subitems feature will be phased out. If you have
this feature enabled in your system, the associated functionality remains available. To
disable the feature, contact your MYOB support provider. |
| Unit Cost | The unit cost of the item, which has been calculated during the cost rollup process. The system copies this cost to the pending cost of the item when you click Update Pending. |
| Material |
The total cost of the BOM materials. [20]insert2023/05/0421:35:22-04:00The system calculates the cost of subassemblies included in the BOM depending on the value of the Level box in the Selection area. The system uses the cost of each material that is a finished good from the Price/Cost tab of the Stock Items (IN202500) form or the Item Warehouse Details (IN204500) form according to the valuation method assigned to the material on the General tab of the Stock Items (IN202500) form as follows:
|
| Fixed Labor | The fixed labor cost. The system calculates this cost as the sum of the setup times for each operation of the bill of material multiplied by the standard rate of the work center assigned to the operation. |
| Variable Labor | The variable labor cost. The system calculates this cost as the sum of the labor time (which is a run time multiplied by the number of run units) for each operation multiplied by the standard rate of the work center assigned to the operation. |
| Fixed Overhead | The total cost of fixed overhead. |
| Variable Overhead | The total cost of variable overhead. |
| Tools | The total cost of tools. |
| Machine | The total machine cost. The system calculates this cost as the sum of the machine time for each operation multiplied by the machine rate per hour. |
| Subcontract | The cost of materials with a type of Subcontract and a subcontract source of Purchase or Ship to Vendor. |
| Ref. Material | The cost of materials that have a type of Subcontract and a subcontract source of Vendor Supplied. The cost of these materials [22]Why then this cost is displayed?2022/09/0619:41:01+03:00is not included in the product cost because the materials are supplied by the vendor. |
| Lot Size |
The lot size, which the system uses to apportion fixed costs, such as fixed labor costs and fixed overhead costs. The system copies the lot size from the Lot Size box of the Stock Items (IN202500) or Item Warehouse Details (IN204500) form. If the lot size is 0, then the system copies the Min Order Qty. value. If this value is also 0, then the system specifies a lot size of 1. |
| Status | The status of the BOM revision. |
| Description | The description of the bill of material. |
| Level | The level of the BOM relative to the parent BOM. For the top-level bill of material, the level is 0. For the subassembly of the top-level BOM, the level is 1. The system defines the levels of all nested subassemblies similarly. |
| Fixed Labor Time | The total setup time for all operations of the BOM. |
| Variable Labor Time | The total run time for all operations of the BOM. |
| Machine Time | The total machine time for all operations of the BOM. |
| Item Class | The item class of the stock item specified in the BOM. |
| Current Standard Cost | The current standard cost if the item has the Standard valuation method. The system copies this value from the Price/Cost tab of the Stock Items (IN202500) or Item Warehouse Details (IN204500) form. |
| Pending Standard Cost | The pending cost if the item has the Standard valuation method. The system updates this value when you update pending costs by clicking the Update Pending button. |