This tab is enabled if the Advanced Job Cost sub-module is in use.
Use Advanced Job Cost to pre-pay invoices relating to input-based jobs. The balance of any pre-paid invoice is carried forward with the job until the pre-paid balance is consumed.
Each option and field on the form is described below. Mandatory options and fields are highlighted in red.
Auto Balance Forward Negative Invoices
Select this option to enable the Advanced Job Cost feature.
Pre-paid Invoice Options
You must assign a job cost activity code to each of the remaining fields. These may have been set up specifically to use with the pre-payment of invoices feature.
Balance Forward Activity Code
Use this activity code to absorb the costs with the pre-paid amount when a JC AR Invoice is saved for the job.
Carried Forward Activity Code
Use this code to carry forward any remaining pre-paid balance against a job pre-paid amount not yet absorbed by subsequently invoiced costs.
Balance Forward Invoice
Use this activity code when a pre-paid invoice is created for a job.
Use estimate variations
Select this option to manage your estimates as one master current estimate, which is a collection of all other estimates for a job. This assumes that all non-current estimates are variations of the master. Do not select this option to edit each estimate per job as a separate entity.
Note: Use this option if you are using revenue recognition and the percentage complete is determined with the job estimate. The current job estimate is the basis for the calculation.
When you select this option, a warning message displays. Click Yes to create a master estimate, which becomes the current one.
If any job already has an estimate called Master, the warning message contains a list of these estimates. If you click Yes on the warning message, Greentree Desktop deletes the existing Master estimates and replace them with the new system-generated master current estimate.
Use date based pricing
Select this option to use date based JC Price Books if the selling prices can be set up as being effective within varied and specified date ranges.
Use Work Centre Plans
Select this option to enable the Work Centre Plan function and to enable these menu options:
If there are any jobs, templates, or quotes in this company that use work centre plans, this option is read-only.
Use Retentions
Select this option if retentions apply to the company you're logged into. When you select this option, it enables the retentions features on these forms:
Revenue recognition type
Select:
Restrict jobs to manager only
Select the option to restrict the user to processing only those jobs in their profit centre group, and for which they are the job manager.
Default percent complete calculation
Select one of these options to use as the basis for calculating percentage complete:
Default revenue calculation
Select one of these options to use as the basis for calculating revenue:
Post recognised revenue to GL
Select this option to post the calculated recognised revenue to the general ledger using the Post Revenue form.
When you select this option, you can specify the pro-rata method and revenue and sales general ledger accounts for each job on the Additional tab of the JC Job Maintenance form.
Sales Code default Rev Recognition a/c
If Post recognised revenue to GL is selected, you can assign the general ledger revenue recognition account to use as the default when setting up new JC Sales Codes.
Revenue pro-rata method
If Post recognised revenue to GL is selected, select an option to use as the revenue pro-rata method during the post revenue process: