In industries like construction, retentions are final amounts of payments held back by a customer or contractor to ensue the satisfactory completion of a project. The retention is generally a percentage of the gross value of work done over a period. Once a contract has been completed in the period mandated by the contract, the subcontractor can submit an invoice to recoup the amount of the retention.
A retention can be — for example, 10% of the contract amount of a job. You can break this down further — for example, pay out 5% of the retention amount after two months, and pay out the remaining 5% two months after that.
You can use Job Costing to:
Greentree calculates and tracks retentions as part of the job invoicing process by tracking the amount a contractor invoices and applying a percentage to each retention break using this formula:
Gross value of invoice x Retention percentage
For example, ...
To set up retentions, you must:
As you add new lines to the invoice, the values on the Retentions tab update. Then, create a pro-forma invoice (which doesn't generate a transaction).
On the Retentions tab of the Job Maintenance form, click the Claim Retentions button.