Supercession Processing

This form is enabled if the Supercessions module is in use, and the option to Use Supercessions is selected on the Options tab of the Module Control form.

You can also access this form from the Inventory Item Maintenance form by clicking the Process button in the Supercession Details area at the base of the item's main form. A supercession is if one or more items replace an existing item — for example because an item has become obsolete, or it has a new item number and new packaging, and the like.

Supercession types are defined on the Supercession Maintenance form. Specific options are for a supercession type, which represent the rules that applies when an item supercession is processed.

When an item is superceded, both the superceded item and the item that superceded it is flagged in the Item Maintenance form so that you can easily see that a supercession has occurred.

To process a supercession, select the item that you are superceding, either by code or description. Once the item is selected, select a Supercession Type. You can select any type that is previously defined on the Supercession Maintenance form.

When you select a type, the remaining details and options on the form uses the type selected. You can edit options before processing a supercession only if the option to Allow default change during process is selected in the Supercession details section on the Options tab of the Inventory Module Control form. If you don't select this option, the supercession type details defaults to the processing form in read-only format, and cannot be edited before processing.

Options Reference

Each option and field on the form is described below. Mandatory options and fields are highlighted in red.

Inventory Quantities

When a supercession type is defined, the Inventory Quantities options define how to deal with on-hand balances of the item that is being superceded:

Sales orders

These options indicate how to treat open sales orders when a supercession is processed:

Reordering Sales History

These options apply to the reordering processes (basic and advanced), and indicate how to use sales history for superceded items and new items when suggested reorder quantities are calculate:

Purchase orders

These options indicate how to treat unreceived purchase orders when a supercession is processed:

Note: The line quantity of the new item is adjusted if the Ratio entered into the New Item Details table is greater than 1.

If you select this option, you must enter a PO Cancel Reason which Greentree Desktop assigns to the cancelled purchase order lines for the superceded item. You can want to set up a special reason code that you can use when a supercession is processed. You can easily tell that a purchase order line was cancelled because of a supercession.

When you select the option to unreceived orders, the new purchase order lines has the same details as the old line, except that the item number is different. The order is received under the new item number. Select this option if you know that the inventory you are expecting to receive is the new item — for example, if the supplier has notified you in advance of a supercession, and indicated that any new inventory being shipped is the new item instead of the old.

Inventory Item Maintenance

These options define whether to update the new item details to be the same as the superceded item details. If the option to Copy all superceded item maintenance details to new item(s) is selected, when the supercession is processed, Greentree Desktop updates the new item with these details of the superceded item: Costing, Pricing, Supplier Details, Reorder Details, UOM details.

Details assigned on the Main tab and general ledger accounts assigned on the Defaults tab on the Inventory Item Maintenance form, the superceded item is assumed by the new item.

Note: If you are processing a one-to-many type supercession, and are copying item details, the costing and pricing details will not be copied.

If you select the copy option, you can enter the new item number into the New Item Details table (free-form), and Greentree Desktop creates it when the supercession is processed. If you don't select the option, you must set up the new item before processing the supercession, so that you can define the details for the new item. You must select an item in the New Item Details table, from a list of items already set up on the Inventory Item Maintenance form.

Whether the option to copy item details is selected or not, you must select an item status code in the Default status to superceded item field. This is the item status code that defaults to the superceded item when the supercession has processed. You can want to define a specific status code to represent supercessions, for example, you can set up a status code of Item Superceded, which is active, but do not allow purchases.

If the option to copy details is selected, you must also select a status code in the Default status to new item(s) field. This is the status code that defaults to the new item when it is created by Greentree Desktop. during supercession processing.

Replace bill of materials

If the old item exists in a manufacturing bill of material (or several), you can run a Bulk Replace BOM process at the same time the supercession is processed. Select the option to replace the old item with the new items in all bills of material that have the old item as a component.

New Item Details Table

If you are copying superceded item details to the new item, enter the new item code (up to 20 characters) and description (up to 30 characters) here. If you are not copying details to the new item, you must select an item from one that has already been set up on the Inventory Item Maintenance form.

If the superceded item is going to be replaced by more than one item, enter or select the number of items in the table (one line for each item).

For each item line, enter a Ratio. This defines the old item to new item ratio when converting quantities if backorders and unreceived purchase orders are being updated. A ratio = 1 indicates that one unit of the superceded item is equal to on unit of the new item. A ratio of 2 indicates that one unit of the superceded item is equal to two units of the new item. When the supercession is processed, the new order lines created by Greentree Desktop. has a quantity = original line quantity x ratio.

Process

Click this button to run the supercession process. The following occurs:

To view details for supercessions that have been processed, you can print a Supercession Audit Report.